Technip Oilexco Shelley Project
Project no: 835
Project name: Technip Oilexco Shelley Project
Project description: Tekmar Subsea
Project completion date: November 2008
Description of product
Provision of Hang-Off Flange, Seal and Split Collar.
The purpose of the hang-off flange, seal and split collar assembly is to provide a structural support for the riser which can be sealed against the riser end fitting.
In principle the hang-off flange shall be installed with the maximum internal bore to permit the pull-thro of the riser end fitting. Followed by the installation of a split seal and collar arrangement.
Project Responsibilities
| • TECHNIP | Owners / operator of platform |
| • TEKMAR | Hang-Off Flange supplier |