• Technip Norge AS

    Tekmar Subsea awarded multi-million pound contract by Technip Norge AS.

    Read news

  • Sapesco Libya

    Tekmar Subsea awarded pipeline repair clamp contract by Sapesco Libya.

    Read news

  • Acergy LARS

    Tekmar Subsea awarded Acergy contract to modify existing LARS.

    Read news

  • Walney Offshore Wind Farm

    Tekmar Energy awarded contract to supply Offshore Wind Farm Turbine cable protection systems to the Walney Offshore Wind Farm.

    Read news

  • Gravity Base Cable Protection System

    Tekmar Energy Supply Gravity Base Cable Protection System Prototype for Subsea Tidal Turbines.

    Read news

  • Tekmar Subsea seal hole in oil pipe wall

    Tekmar Subsea seal hole in oil pipe wall, saving 3,000 barrels of oil per day.

    Read news

  • Flare Stack Reinforcement

    Tekmar Subsea design and manufacture all equipment on a 21 day schedule, successfully install off the coast of Egypt.

    Read news

  • Teklink Cost Savings

    Teklink Achieves 70% Reduction in costs in offshore wind farm installations.

    Read news

Acergy Swingframe Refurbishment

Project no: 766

Project name: Acergy Swingframe Refurbishment

Project description: Tekmar Subsea

Project completion date: June 2009

 

Description of product

 

Fixed swingframe and sheave

The original X-90 units were supplied with fixed sheaves to suit the smaller winches which limited the length of the cable drum and degree of allowable fleet of the cable.

 

Fleeting Swingframe

Deepwater operations required larger winches and greater fleet angles. A fleeting swingframe was supplied which allowed the entire assembly to rotate, fitted with a hydraulic valve to stop the rotation during vehicle parking operations.

 

Fleeting sheave

To remove the need for the hydraulic function the swingframe was fixed and the sheave was allowed to fleet. The assembly was supported by an upper and lower pivot arrangement. Pins and bushes were used due to slow and partial angular movement.

 

This current design has been in operation for five years and has been installed on twelve systems. The pin and bush arrangement requires lubrication to reduce the friction to an acceptable level to allow automatic fleeting.

 

Client benefits provided by solution

This upgrade will also have a positive impact to Acergy as currently there are two different lengths of swingframes to suit the 1480 MBD umbilical. The new design will be shorter which will mean Acergy can accommodate a larger stack height on the A-frame.

 

Project Responsibilities

• ACERGY Owners / operator of platform
• TEKMAR Water-stop seal supplier